Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 20059286 | Bagheri and Bhelakha multi village water supply scheme | 605.61 | 248.04 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 49 | 49 | No | 0 | NA | No | 46259.97 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Pratappur | Bagheri | 433257 | Bagheri | 337 | 334 | 99 | Work In Progress | Not Certified |
| 2 | Prayagraj | Pratappur | Bhelakha | 433277 | Bhelakha | 310 | 299 | 96 | Work In Progress | Not Certified |
| 3 | Prayagraj | Pratappur | Bhelakha | 433278 | Bindrawan | 96 | 75 | 78 | Work In Progress | Not Certified |
| 4 | Prayagraj | Pratappur | Bhelakha | 433279 | Puri Rudiye | 31 | 1 | 3 | Work In Progress | Not Certified |