Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20059294
SCHEME NAME
Bariyanwa and Pure misir multi village water supply scheme
ESTIMATED COST
518.02
EXPENDITURE
229.03
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
9
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
42
Procured
42
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
39037.26
Meter
Length Laid
39037.00
Meter
Scheme Assigned Villages
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Pratappur | Pure Misir | 433250 | Pure Misir | 94 | 90 | 96% | Work In Progress | Not Certified |
| 2 | Prayagraj | Pratappur | Pure Misir | 433251 | Chakiya Urf Chak Todar | 52 | 40 | 77% | Work In Progress | Not Certified |
| 3 | Prayagraj | Pratappur | Pure Misir | 433252 | Baghapur | 40 | 34 | 85% | Work In Progress | Not Certified |
| 4 | Prayagraj | Pratappur | Pure Misir | 433253 | Bhoja Raja | 49 | 38 | 78% | Work In Progress | Not Certified |
| 5 | Prayagraj | Pratappur | Bariyanwa | 433263 | Bariyanwa | 157 | 129 | 82% | Work In Progress | Not Certified |
| 6 | Prayagraj | Pratappur | Bariyanwa | 433265 | Majhiyari Ta. Chhatauna | 52 | 44 | 85% | Work In Progress | Not Certified |
| 7 | Prayagraj | Pratappur | Saidaha Sathar | 433266 | MAJHIYARI VARI | 17 | 12 | 71% | Work In Progress | Not Certified |
| 8 | Prayagraj | Pratappur | Bariyanwa | 433267 | Pure Deeh | 85 | 81 | 95% | Work In Progress | Not Certified |
| 9 | Prayagraj | Pratappur | Bariyanwa | 699646 | NIMIWARI | 122 | 112 | 92% | Work In Progress | Not Certified |