Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20059348 | Paraura,Diodas & Haldikhurd | 500.04 | 265.72 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 20015.00 | 20000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Mirganj | Diodas | 403227 | Diodas | 287 | 287 | 100 | Har Gar Jal | Not Certified |
| 2 | Bareilly | Mirganj | Paraura | 403228 | Paraura | 474 | 474 | 100 | Har Gar Jal | Not Certified |
| 3 | Bareilly | Mirganj | Haldikhurd | 403277 | Haldikhurd | 314 | 314 | 100 | Har Gar Jal | Not Certified |