Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20059360
SCHEME NAME
Deoria abdullaganj,Raiya Nagla & Sisaun Khera
ESTIMATED COST
559.50
EXPENDITURE
360.39
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
42
Procured
42
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24928.00
Meter
Length Laid
24900.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Mirganj | Sisaun Khera | 403263 | Sisaun Khera | 233 | 233 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bareilly | Mirganj | Deoria Abdullaganj | 403265 | Deoria Abdullaganj | 575 | 575 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bareilly | Mirganj | Raiya Nagla | 403268 | Raiya Nagla | 335 | 335 | 100% | Har Ghar Jal | Not Certified |