Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20059406
SCHEME NAME
MOHAMMAD HAYATPUR VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
291.20
EXPENDITURE
156.12
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11290.00
Meter
Length Laid
11010.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Bilari | Mohammad Hayatpur | 388650 | Mohammad Hayatpur | 371 | 370 | 100% | Work In Progress | Not Certified |
| 2 | Moradabad | Bilari | Mohammad Hayatpur | 388651 | Bahoranpur Narauli | 197 | 197 | 100% | Har Ghar Jal | Not Certified |