Scheme Details
DISTRICT
Gorakhpur
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20059413
SCHEME NAME
MATIARI GP JJM
ESTIMATED COST
162.48
EXPENDITURE
24.64
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
12
Procured
12
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6730.00
Meter
Length Laid
6702.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Pali | Matiari | 454920 | Matiari | 128 | 128 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Pali | Matiari | 454921 | Matiara | 106 | 105 | 99% | Work In Progress | Not Certified |
| 3 | Gorakhpur | Pali | Matiari | 454922 | Kushma Kala | 31 | 14 | 45% | Work In Progress | Not Certified |
| 4 | Gorakhpur | Pali | Matiari | 454923 | Amsar | 146 | 133 | 91% | Work In Progress | Not Certified |