Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20059425 | MUNDIA NASIR, BAIKENIA KALEKHAN & SINGOTHI | 492.11 | 252.60 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 19682.00 | 19000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Damkhoda | Mundia Nasir | 402951 | Mundia Nasir | 230 | 230 | 100 | Har Gar Jal | Not Certified |
| 2 | Bareilly | Damkhoda | Mundia Nasir | 402952 | Shekhpur | 60 | 60 | 100 | Har Gar Jal | Not Certified |
| 3 | Bareilly | Damkhoda | Baikenia Kalekhan | 402955 | Baikenia Kalekhan | 206 | 206 | 100 | Har Gar Jal | Not Certified |
| 4 | Bareilly | Damkhoda | Singothi | 403006 | Singothi | 423 | 423 | 100 | Har Gar Jal | Not Certified |