S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Bareilly NCC Ltd. 20059453 NARAHI NAUA NAGLA & BISHI RAMPURA & SUNAUR Water Supply 473.99 258.27 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 1 35 35 Yes 0 NA No 20344.00 20200.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Bareilly Bhadpura Bishi Rampura 404052 Bishi Rampura 180 180 100 Har Gar Jal Not Certified
2 Bareilly Bhadpura Sunaur 404076 Sunaur 282 282 100 Har Gar Jal Not Certified
3 Bareilly Bhadpura Sunaur 404077 Desh Nagar 85 85 100 Har Gar Jal Not Certified
4 Bareilly Bhadpura Narahi Naua Nagla 404078 Narahi Naua Nagla 389 389 100 Har Gar Jal Not Certified