Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Rithwik-Koya (JV) | 20059476 | HARIHARPUR GP JJM | 203.57 | 81.64 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 6770.00 | 7270.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Hariharpur | 455934 | Hariharpur | 52 | 52 | 100 | Har Gar Jal | Not Certified |
| 2 | Gorakhpur | Uruwa | Hariharpur | 455935 | Londra | 51 | 51 | 100 | Har Gar Jal | Not Certified |
| 3 | Gorakhpur | Uruwa | Hariharpur | 455936 | Sahdevapur | 155 | 155 | 100 | Har Gar Jal | Not Certified |
| 4 | Gorakhpur | Uruwa | Hariharpur | 455937 | Bathua Bujurg | 128 | 128 | 100 | Har Gar Jal | Not Certified |