Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Rithwik-Koya (JV) | 20059503 | BARWALMAFI JJM | 198.71 | 105.49 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 12290.00 | 12290.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Piprauli | Barwal Mafi | 455179 | Barwal Mafi | 222 | 222 | 100 | Har Gar Jal | Not Certified | 
| 2 | Gorakhpur | Piprauli | Barwal Mafi | 455180 | Bachhaura | 8 | 1 | 12 | Work In Progress | Not Certified | 
| 3 | Gorakhpur | Piprauli | Barwal Mafi | 455181 | Tal Nagari | 5 | 1 | 20 | Work In Progress | Not Certified | 
| 4 | Gorakhpur | Piprauli | Barwal Mafi | 455182 | Jotrehara | 32 | 32 | 100 | Har Gar Jal | Not Certified |