Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20059517 | NAULI & RATANGARH Water Supply Scheme | 512.70 | 219.89 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 29985.00 | 28996.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Baheri | Nauli | 402639 | Nauli | 98 | 98 | 100 | Har Gar Jal | Not Certified |
| 2 | Bareilly | Baheri | Nauli | 402640 | Bahunagar Urf Sirsa | 96 | 96 | 100 | Har Gar Jal | Not Certified |
| 3 | Bareilly | Baheri | Nauli | 402641 | Piparia Ganesh | 76 | 76 | 100 | Har Gar Jal | Not Certified |
| 4 | Bareilly | Baheri | Nauli | 402642 | Patparagunj | 61 | 61 | 100 | Har Gar Jal | Not Certified |
| 5 | Bareilly | Baheri | Ratangarh | 402645 | Ratangarh | 210 | 206 | 98 | Work In Progress | Not Certified |
| 6 | Bareilly | Baheri | Ratangarh | 402646 | Wasadandi | 66 | 61 | 92 | Work In Progress | Not Certified |
| 7 | Bareilly | Baheri | Ratangarh | 402647 | Naula | 19 | 19 | 100 | Har Gar Jal | Not Certified |