Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20059531
SCHEME NAME Rahilamau & Baisara Water Supply Scheme
ESTIMATED COST 270.85
EXPENDITURE 143.96
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9285.00 Meter
Length Laid 7364.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Fatehpur Rahilamau 434660 Rahilamau 162 156 96% Work In Progress Not Certified
2 Barabanki Fatehpur Rahilamau 434661 Jagaipur 127 120 94% Work In Progress Not Certified
3 Barabanki Fatehpur Baisara 434662 Baisara 177 170 96% Work In Progress Not Certified