| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Rithwik-Koya (JV) | 20059540 | RAMPUR SANATH JJM | 290.03 | 114.49 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 20350.00 | 19830.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Rampursanath | 455961 | Rampur Sanath | 68 | 3 | 4 | Work In Progress | Not Certified | 
| 2 | Gorakhpur | Uruwa | Rampursanath | 455962 | Pipara Pathak | 18 | 18 | 100 | Har Gar Jal | Not Certified | 
| 3 | Gorakhpur | Uruwa | Rampursanath | 455963 | Golipar | 84 | 84 | 100 | Har Gar Jal | Not Certified | 
| 4 | Gorakhpur | Uruwa | Rampursanath | 455964 | Tadawa Bahalim | 78 | 1 | 1 | Work In Progress | Not Certified | 
| 5 | Gorakhpur | Uruwa | Rampursanath | 455965 | Math Bhatari | 107 | 106 | 99 | Work In Progress | Not Certified | 
| 6 | Gorakhpur | Uruwa | Rampursanath | 696393 | MASUR CHAK | 3 | 0 | 0 | Work In Progress | Not Certified |