Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | PNC-SPML-JV | 20059554 | Rajaipur & Muskipur Water Supply Scheme | 312.06 | 144.69 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 11843.00 | 10758.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Masauli | Rajai Pur | 435413 | Rajai Pur | 139 | 138 | 99 | Work In Progress | Not Certified | 
| 2 | Barabanki | Masauli | Rajai Pur | 435414 | Gotva Guari | 105 | 105 | 100 | Har Gar Jal | Not Certified | 
| 3 | Barabanki | Masauli | Rajai Pur | 435415 | Katra | 12 | 11 | 92 | Work In Progress | Not Certified | 
| 4 | Barabanki | Masauli | Mushki Nagar | 435423 | Mushki Nagar | 245 | 244 | 100 | Work In Progress | Not Certified |