Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20059565
SCHEME NAME
Rahpur & Chandoora Water Supply Scheme
ESTIMATED COST
419.73
EXPENDITURE
259.32
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18389.00
Meter
Length Laid
18020.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Suratganj | Chandoora | 434817 | Chandoora | 482 | 479 | 99% | Work In Progress | Not Certified |
| 2 | Barabanki | Suratganj | Raipur | 434830 | Raipur | 285 | 279 | 98% | Work In Progress | Not Certified |
| 3 | Barabanki | Suratganj | Raipur | 434831 | Imlipur | 98 | 95 | 97% | Work In Progress | Not Certified |
| 4 | Barabanki | Suratganj | Raipur | 434832 | Sohai | 81 | 77 | 95% | Work In Progress | Not Certified |