Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20059602
SCHEME NAME Miranagar & Khaira Water Supply Scheme
ESTIMATED COST 297.04
EXPENDITURE 184.33
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11693.00 Meter
Length Laid 11693.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Fatehpur Khaira 434638 Khaira 157 155 99% Work In Progress Not Certified
2 Barabanki Fatehpur Khaira 434639 Behti 114 114 100% Har Ghar Jal Not Certified
3 Barabanki Fatehpur Khaira 434640 Lalpur 82 80 98% Work In Progress Not Certified
4 Barabanki Fatehpur Mirnagar 434646 Mirnagar 244 242 99% Work In Progress Not Certified