Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | PNC-SPML-JV | 20059613 | Samarda & Maulabad Water Supply Scheme | 249.89 | 117.26 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 8279.00 | 7945.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Nindaura | Maulabad | 434459 | Maulabad | 188 | 183 | 97 | Work In Progress | Not Certified |
| 2 | Barabanki | Nindaura | Samarda | 434537 | Samarda | 244 | 238 | 98 | Work In Progress | Not Certified |
| 3 | Barabanki | Nindaura | Samarda | 434538 | Kaprapur | 32 | 27 | 84 | Work In Progress | Not Certified |