Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20059665 | GAJIPUR GP wss | 200.11 | 99.45 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 17 | 17 | Yes | 0 | NA | No | 8641.00 | 15030.30 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Harraiya | Gajipur | 449625 | Gajipur | 156 | 155 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Harraiya | Gajipur | 449626 | Mahulani | 31 | 30 | 97 | Work In Progress | Not Certified |
| 3 | Basti | Harraiya | Gajipur | 449627 | Jaimunipur | 54 | 53 | 98 | Work In Progress | Not Certified |
| 4 | Basti | Harraiya | Gajipur | 449628 | Bithalapur | 67 | 67 | 100 | Har Gar Jal | Not Certified |