| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20059688 | ASHAAPUR & KHEMAPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 451.18 | 126.33 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 30 | 30 | NA | 0 | NA | No | 27275.00 | 25854.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Rampur | ASHA PUR | 470885 | ASHAPUR | 360 | 296 | 82 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Rampur | Khemapur | 470890 | Dubeypur | 91 | 61 | 67 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Rampur | Khemapur | 470891 | Khemapur | 170 | 170 | 100 | Har Gar Jal | Not Certified |