Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20059720 | DAGHELA (GOGP) JJM | 574.94 | 363.68 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 28293.00 | 26271.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Bharkhani | Daghela | 412232 | Daghela | 340 | 340 | 100 | Har Gar Jal | Certified |
| 2 | Hardoi | Bharkhani | Mahmoodpur | 412285 | Mahmoodpur | 189 | 188 | 99 | Work In Progress | Not Certified |
| 3 | Hardoi | Bharkhani | Mahmoodpur | 412287 | Tera | 110 | 109 | 99 | Work In Progress | Not Certified |
| 4 | Hardoi | Bharkhani | Hathaura | 412332 | Hathaura | 361 | 361 | 100 | Har Gar Jal | Not Certified |