Scheme Details
DISTRICT
Siddharth Nagar
AGENCY
VSA
SCHEME ID
20059764
SCHEME NAME
BALIBHADARPUR GOVARAHA AND MAU NANKAR WSS
ESTIMATED COST
263.62
EXPENDITURE
167.18
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10475.00
Meter
Length Laid
10475.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Khuniyaon | Mau Nankar | 448393 | Mau Nankar | 191 | 176 | 92% | Work In Progress | Not Certified |
| 2 | Siddharth Nagar | Khuniyaon | Balibhadra Pur Urf Gobaraha | 448394 | Balibhadra Pur Gobaraha | 107 | 94 | 88% | Work In Progress | Not Certified |
| 3 | Siddharth Nagar | Khuniyaon | Balibhadra Pur Urf Gobaraha | 448396 | Rajwapur Urf Belwa | 26 | 26 | 100% | Har Ghar Jal | Not Certified |