Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20059786 | GAURA UDAIPUR (GOGP) JJM | 524.73 | 234.46 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 24355.00 | 22205.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Bharkhani | CHAUDA RAI | 412220 | CHAUDA RAI | 465 | 459 | 99 | Work In Progress | Not Certified |
| 2 | Hardoi | Bharkhani | Sahjanpur | 412311 | Sahjanpur | 312 | 309 | 99 | Work In Progress | Not Certified |
| 3 | Hardoi | Bharkhani | Gaura Udaipur | 412312 | Gaura Udaipur | 251 | 242 | 96 | Work In Progress | Not Certified |