Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20059815 | HARAYA MISRA GP wss | 205.67 | 120.05 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 17 | 17 | Yes | 0 | NA | No | 9080.00 | 8000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Rudhauli | Haraya Misra | 450571 | Parsatiwari | 81 | 80 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Rudhauli | Haraya Misra | 450572 | Parasia | 46 | 45 | 98 | Work In Progress | Not Certified |
| 3 | Basti | Rudhauli | Haraya Misra | 450573 | Haraya Misra | 94 | 93 | 99 | Work In Progress | Not Certified |
| 4 | Basti | Rudhauli | Haraya Misra | 450574 | Khamheria | 31 | 30 | 97 | Work In Progress | Not Certified |
| 5 | Basti | Rudhauli | Haraya Misra | 450575 | Sukarouli | 81 | 80 | 99 | Work In Progress | Not Certified |