Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20059822
SCHEME NAME
JAMALAPUR & RANIPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
440.21
EXPENDITURE
194.48
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
32335.00
Meter
Length Laid
26350.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mariyahun | Ranipur | 469708 | Ranipur | 47 | 47 | 100% | Har Ghar Jal | Not Certified |
| 2 | Jaunpur | Mariyahun | Ranipur | 469709 | Barauli | 183 | 137 | 75% | Work In Progress | Not Certified |
| 3 | Jaunpur | Mariyahun | Jamalapur | 469710 | Jamalapur | 236 | 172 | 73% | Work In Progress | Not Certified |
| 4 | Jaunpur | Mariyahun | Jamalapur | 469711 | Chak Dost Jamalpur | 13 | 1 | 8% | Work In Progress | Not Certified |
| 5 | Jaunpur | Mariyahun | Jamalapur | 469712 | Jagdishpur | 74 | 29 | 39% | Work In Progress | Not Certified |