Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20059823 | CHHIBRA & AILIYA GP wss | 304.98 | 185.23 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 17445.00 | 19058.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Kudaraha | Aailiya | 451717 | Agya Urf Bhitha | 82 | 81 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Kudaraha | Aailiya | 451718 | Burhiya Koil Urf Bandi Baboo | 1 | 1 | 100 | Har Gar Jal | Not Certified |
| 3 | Basti | Kudaraha | Aailiya | 451719 | Ailiya | 156 | 156 | 100 | Har Gar Jal | Not Certified |
| 4 | Basti | Kudaraha | Chhibra | 451720 | Chhibra | 176 | 176 | 100 | Har Gar Jal | Not Certified |
| 5 | Basti | Kudaraha | Aailiya | 451721 | Sir Gotwa | 54 | 54 | 100 | Har Gar Jal | Not Certified |
| 6 | Basti | Kudaraha | Chhibra | 451732 | Ismailpur | 116 | 116 | 100 | Har Gar Jal | Not Certified |
| 7 | Basti | Kudaraha | Chhibra | 680386 | Civil Jail | 48 | 48 | 100 | Har Gar Jal | Not Certified |