Scheme Details
DISTRICT
Basti
AGENCY
Megha
SCHEME ID
20059823
SCHEME NAME
CHHIBRA & AILIYA GP wss
ESTIMATED COST
304.98
EXPENDITURE
214.02
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17445.00
Meter
Length Laid
19058.00
Meter
Scheme Assigned Villages
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Kudaraha | Aailiya | 451717 | Agya Urf Bhitha | 82 | 81 | 99% | Work In Progress | Not Certified |
| 2 | Basti | Kudaraha | Aailiya | 451718 | Burhiya Koil Urf Bandi Baboo | 1 | 1 | 100% | Har Ghar Jal | Not Certified |
| 3 | Basti | Kudaraha | Aailiya | 451719 | Ailiya | 156 | 156 | 100% | Har Ghar Jal | Not Certified |
| 4 | Basti | Kudaraha | Chhibra | 451720 | Chhibra | 176 | 176 | 100% | Har Ghar Jal | Not Certified |
| 5 | Basti | Kudaraha | Aailiya | 451721 | Sir Gotwa | 54 | 54 | 100% | Har Ghar Jal | Not Certified |
| 6 | Basti | Kudaraha | Chhibra | 451732 | Ismailpur | 116 | 116 | 100% | Har Ghar Jal | Not Certified |
| 7 | Basti | Kudaraha | Chhibra | 680386 | Civil Jail | 48 | 48 | 100% | Har Ghar Jal | Not Certified |