Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Pilibhit VISHVARAJ 20059984 KABEERGANJ-EAST + 2 MULTI GP WATER SUPPLY SCHEME 523.60 269.74 view more

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 0 37 37 Yes 0 NA No 21560.00 21500.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Pilibhit Puranpur Vijai Nagar 405447 Vijai Nagar 143 129 90 Work In Progress Not Certified
2 Pilibhit Puranpur Vijai Nagar 405448 Gautam Nagar 136 118 87 Work In Progress Not Certified
3 Pilibhit Puranpur Kabeerganj 405488 Kabeerganj 910 904 99 Work In Progress Not Certified
4 Pilibhit Puranpur Kuthia Gudia 405535 Kuthia Gudia 349 316 91 Work In Progress Not Certified