Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20059998
SCHEME NAME
CHINAURA MUSTQIL + 3 MULTI GP WATER SUPPLY SCHEME
ESTIMATED COST
625.91
EXPENDITURE
450.33
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
22336.00
Meter
Length Laid
21736.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Lalaurikhera | Jiraunia | 404766 | Jiraunia | 594 | 524 | 88% | Work In Progress | Not Certified |
| 2 | Pilibhit | Lalaurikhera | Chinaura Mustqil | 404774 | Chinaura Mustqil | 229 | 229 | 100% | Har Ghar Jal | Certified |
| 3 | Pilibhit | Lalaurikhera | Shathrapur Mus0 | 404775 | Bhaisaha Mustqil | 86 | 67 | 78% | Work In Progress | Not Certified |
| 4 | Pilibhit | Lalaurikhera | Shathrapur Mus0 | 404776 | Sathrapur Mustqil | 111 | 110 | 99% | Work In Progress | Not Certified |
| 5 | Pilibhit | Lalaurikhera | Raipur Mustqil | 404856 | Raipur Mustqil | 173 | 150 | 87% | Work In Progress | Not Certified |
| 6 | Pilibhit | Lalaurikhera | Chinaura Mustqil | 681315 | Chinaura Ehatmali | 35 | 35 | 100% | Har Ghar Jal | Certified |