Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20060053
SCHEME NAME
Gangauli Water Supply Scheme
ESTIMATED COST
210.93
EXPENDITURE
100.67
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6720.00
Meter
Length Laid
5120.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Nindaura | Gangauli | 434413 | Gangauli | 232 | 229 | 99% | Work In Progress | Not Certified |
| 2 | Barabanki | Nindaura | Gangauli | 434415 | Niamatpur | 63 | 61 | 97% | Work In Progress | Not Certified |