Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Barabanki PNC-SPML-JV 20060082 Chedanagar & Saray Akbrabad Water Supply Scheme 244.67 131.36 view more

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 1 20 20 Yes 0 NA No 6130.00 6120.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Barabanki Banki Chheda Nagar 435207 Chheda Nagar 286 283 99 Work In Progress Not Certified
2 Barabanki Banki Saray Akbarabad 435214 Saray Akbarabad 169 169 100 Har Gar Jal Not Certified