Scheme Details
DISTRICT
Sitapur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20060275
SCHEME NAME
MOHARASA - HARIRAMPUR
ESTIMATED COST
406.89
EXPENDITURE
226.85
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14048.00
Meter
Length Laid
12104.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Hargaon | Harirampur | 410349 | Bhaisaha | 79 | 79 | 100% | Har Ghar Jal | Not Certified |
| 2 | Sitapur | Hargaon | Harirampur | 410350 | Harirampur | 332 | 321 | 97% | Work In Progress | Not Certified |
| 3 | Sitapur | Hargaon | Harirampur | 410351 | Nayamatpur Kaima | 56 | 53 | 95% | Work In Progress | Not Certified |
| 4 | Sitapur | Hargaon | Moharsa | 410375 | Mohrasa | 366 | 329 | 90% | Work In Progress | Not Certified |