Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20060446 | TILIA GHATWASA (GOGP) JJM | 454.85 | 261.35 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 18846.00 | 18846.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Harpalpur | TILIYA GHATWASA | 412492 | TILIYA GHATWASA | 410 | 410 | 100 | Har Gar Jal | Not Certified | 
| 2 | Hardoi | Harpalpur | LALUAMAU | 412546 | LALUAMAU | 586 | 558 | 95 | Work In Progress | Not Certified |