Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Hardoi NCC Ltd. 20060456 ALIGARH (GOGP) JJM 487.88 289.47 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 0 37 37 Yes 0 NA No 18759.00 18759.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Hardoi Bilagram ALLIGARH 412652 ALLIGARH 330 330 100 Har Gar Jal Certified
2 Hardoi Bilagram ALLIGARH 412653 ITAULI 141 141 100 Har Gar Jal Certified
3 Hardoi Bilagram Panyori 412751 Panyori 156 155 99 Work In Progress Not Certified
4 Hardoi Bilagram Panyori 412752 Akhtiyarpur 156 153 98 Work In Progress Not Certified