Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pilibhit
AGENCY VISHVARAJ
SCHEME ID 20060457
SCHEME NAME chandpura+ 1 multi gp water supply scheme
ESTIMATED COST 397.99
EXPENDITURE 245.64
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 13216.00 Meter
Length Laid 12616.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Bisalpur Chandpura 405214 Chandpura 561 560 100% Work In Progress Not Certified
2 Pilibhit Bisalpur Kangawa 405215 Kangawan 262 261 100% Work In Progress Not Certified