Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20060523
SCHEME NAME
BAHADURPUR GP WATER SUPPLY SCHEME
ESTIMATED COST
303.32
EXPENDITURE
214.88
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11125.00
Meter
Length Laid
11000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Puranpur | Manharia | 405660 | Maniharia | 304 | 301 | 99% | Work In Progress | Not Certified |
| 2 | Pilibhit | Puranpur | Bahadurpur Bujurg | 405661 | Bahadurpur Bujurg | 263 | 263 | 100% | Har Ghar Jal | Certified |