Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20060636
SCHEME NAME DABILHA & RAMPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 340.48
EXPENDITURE 156.55
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 0
O.P. Unit Done 0
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 20260.00 Meter
Length Laid 18778.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Mariyahun Dabilaha 469776 Dabilaha 204 204 100% Har Ghar Jal Not Certified
2 Jaunpur Mariyahun Rampur 469777 Saraiya 79 79 100% Har Ghar Jal Not Certified