Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20060685
SCHEME NAME
Sunderpur + 2 MULTI GP WATER SUPPLY SCHEME
ESTIMATED COST
727.70
EXPENDITURE
406.08
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
10
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
64645.00
Meter
Length Laid
64445.00
Meter
Scheme Assigned Villages
10 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Puranpur | Gopalpur | 405332 | Gopalpur | 428 | 427 | 100% | Work In Progress | Not Certified |
| 2 | Pilibhit | Puranpur | Pandria | 405549 | Pandria | 146 | 145 | 99% | Work In Progress | Not Certified |
| 3 | Pilibhit | Puranpur | Pandria | 405551 | Birampur | 14 | 1 | 7% | Work In Progress | Not Certified |
| 4 | Pilibhit | Puranpur | Pandria | 405552 | Jagatpur T. Gajraula | 28 | 1 | 4% | Work In Progress | Not Certified |
| 5 | Pilibhit | Puranpur | Sunderpur | 405705 | Sunderpur | 64 | 63 | 98% | Work In Progress | Not Certified |
| 6 | Pilibhit | Puranpur | Sunderpur | 405708 | Mandanpur Khurd | 20 | 1 | 5% | Work In Progress | Not Certified |
| 7 | Pilibhit | Puranpur | Sunderpur | 405710 | Shimbhua | 50 | 50 | 100% | Har Ghar Jal | Not Certified |
| 8 | Pilibhit | Puranpur | Sunderpur | 405711 | Pooranpur Kurraiya | 36 | 27 | 75% | Work In Progress | Not Certified |
| 9 | Pilibhit | Puranpur | Sunderpur | 405713 | Tandola | 34 | 1 | 3% | Work In Progress | Not Certified |
| 10 | Pilibhit | Puranpur | Sunderpur | 405714 | Raghunathpur J.sikrahna | 26 | 21 | 81% | Work In Progress | Not Certified |