Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20060828 | RAMPUR FAKIRE + 1 MULTI GP WATER SUPPLY SCHEME | 528.88 | 306.87 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 29780.00 | 29700.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Puranpur | Rampur Fakire | 405568 | Rampur Fakire | 517 | 511 | 99 | Work In Progress | Not Certified |
| 2 | Pilibhit | Puranpur | Rampur Fakire | 405569 | Navdia Maksudpur | 16 | 10 | 62 | Work In Progress | Not Certified |
| 3 | Pilibhit | Puranpur | Rampur Fakire | 405570 | Biharipur M. Rampur Fakire | 35 | 32 | 91 | Work In Progress | Not Certified |
| 4 | Pilibhit | Puranpur | Sabalpur M. Rampur Fakire | 405593 | Sabalpur M. Rampur Fakire | 407 | 400 | 98 | Work In Progress | Not Certified |
| 5 | Pilibhit | Puranpur | Sabalpur M. Rampur Fakire | 405594 | Kataiya | 24 | 1 | 4 | Work In Progress | Not Certified |
| 6 | Pilibhit | Puranpur | Sabalpur M. Rampur Fakire | 405595 | Amraiya Khurd | 14 | 7 | 50 | Work In Progress | Not Certified |