Scheme Details
DISTRICT Pilibhit
AGENCY VISHVARAJ
SCHEME ID 20060831
SCHEME NAME Simraya T. Ghungchihai GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 250.22
EXPENDITURE 186.06
AUTOMATION STATUS Not Integrated
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 6
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 8
Transformer Procured NA
Work Status No
Distribution Line
Total Length 20814.00 Meter
Length Laid 20714.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

6 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Puranpur Simraya T. Ghungchihai 405317 Simraya T. Ghungchihai 165 165 100% Har Ghar Jal Certified
2 Pilibhit Puranpur Simraya T. Ghungchihai 405318 Fattepur 116 116 100% Har Ghar Jal Certified
3 Pilibhit Puranpur Simraya T. Ghungchihai 405319 Karobojh 28 28 100% Har Ghar Jal Certified
4 Pilibhit Puranpur Simraya T. Ghungchihai 405320 Bhagwantpur M. Karobojh 39 39 100% Har Ghar Jal Certified
5 Pilibhit Puranpur Simraya T. Ghungchihai 405321 Lohanna 15 15 100% Har Ghar Jal Certified
6 Pilibhit Puranpur Simraya T. Ghungchihai 405322 Sohanna 13 13 100% Har Ghar Jal Certified