Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20060888
SCHEME NAME
Udara +1 GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
383.20
EXPENDITURE
304.81
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
9
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
41327.00
Meter
Length Laid
41285.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Amaria | Udara | 404548 | Udara | 74 | 73 | 99% | Work In Progress | Not Certified |
| 2 | Pilibhit | Amaria | Udara | 404549 | Bhadsara | 50 | 48 | 96% | Work In Progress | Not Certified |
| 3 | Pilibhit | Amaria | Udara | 404550 | Jamgahan | 55 | 50 | 91% | Work In Progress | Not Certified |
| 4 | Pilibhit | Amaria | Udara | 404551 | Faridpur Hasan | 50 | 48 | 96% | Work In Progress | Not Certified |
| 5 | Pilibhit | Amaria | Udara | 404552 | Mohanpur | 24 | 12 | 50% | Work In Progress | Not Certified |
| 6 | Pilibhit | Amaria | Balliya | 404554 | Balliya | 169 | 166 | 98% | Work In Progress | Not Certified |
| 7 | Pilibhit | Amaria | Balliya | 404555 | Kesarpur | 45 | 41 | 91% | Work In Progress | Not Certified |
| 8 | Pilibhit | Amaria | Balliya | 404556 | Hetam Dandi | 39 | 31 | 79% | Work In Progress | Not Certified |
| 9 | Pilibhit | Amaria | Balliya | 404557 | Balpur Mafi | 66 | 41 | 62% | Work In Progress | Not Certified |