Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20060899
SCHEME NAME
KHIRI NAUBARAMAD +1 MULTI GP WATER SUPPLY SCHEME
ESTIMATED COST
385.50
EXPENDITURE
303.74
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
8
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
49945.00
Meter
Length Laid
49345.00
Meter
Scheme Assigned Villages
8 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Puranpur | Loharpura | 405368 | Loharpura | 161 | 147 | 91% | Work In Progress | Not Certified |
| 2 | Pilibhit | Puranpur | Loharpura | 405369 | Arjunpur | 46 | 31 | 67% | Work In Progress | Not Certified |
| 3 | Pilibhit | Puranpur | Loharpura | 405370 | Khakra | 10 | 2 | 20% | Work In Progress | Not Certified |
| 4 | Pilibhit | Puranpur | Loharpura | 405371 | Bhikampur | 40 | 11 | 28% | Work In Progress | Not Certified |
| 5 | Pilibhit | Puranpur | Khiri Naubaramad | 405543 | Khiri Naubaramad | 143 | 142 | 99% | Work In Progress | Not Certified |
| 6 | Pilibhit | Puranpur | Khiri Naubaramad | 405544 | Akbarpur | 12 | 3 | 25% | Work In Progress | Not Certified |
| 7 | Pilibhit | Puranpur | Khiri Naubaramad | 405545 | Kiratpur T. Madho Tanda | 80 | 79 | 99% | Work In Progress | Not Certified |
| 8 | Pilibhit | Puranpur | Khiri Naubaramad | 405546 | Tulsipur | 73 | 71 | 97% | Work In Progress | Not Certified |