Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pilibhit
AGENCY VISHVARAJ
SCHEME ID 20060914
SCHEME NAME ABHAIPURA CHAINA NAKTI + 1 MULTI GP WATER SUPPLY SCHEME
ESTIMATED COST 386.20
EXPENDITURE 248.05
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12699.00 Meter
Length Laid 12600.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Bisalpur Mahadewa 405197 Mahadewa 372 353 95% Work In Progress Not Certified
2 Pilibhit Bisalpur Abhaipur Chaina Nakti 405249 Abhaipur Chaina Nakti 343 343 100% Har Ghar Jal Certified
3 Pilibhit Bisalpur Abhaipur Chaina Nakti 405250 Bhagawantpur Karor Must. 110 110 100% Har Ghar Jal Certified