Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20060922
SCHEME NAME
MANPUR MARORI + 2 MULTI GP WATER SUPPLY SCHEME
ESTIMATED COST
485.00
EXPENDITURE
333.42
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16076.00
Meter
Length Laid
15476.00
Meter
Scheme Assigned Villages
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bisalpur | BARSI URF BARSIA | 405212 | BARSI BALEY URF BARSIA | 196 | 188 | 96% | Work In Progress | Not Certified |
| 2 | Pilibhit | Bisalpur | BARSI URF BARSIA | 405213 | CHAUKHANDI | 148 | 148 | 100% | Har Ghar Jal | Not Certified |
| 3 | Pilibhit | Bisalpur | Daulatpur Heera | 405254 | Daulatpur Heera | 339 | 339 | 100% | Har Ghar Jal | Not Certified |
| 4 | Pilibhit | Bisalpur | Manpur Marori | 405272 | Manpur Marori | 148 | 148 | 100% | Har Ghar Jal | Not Certified |
| 5 | Pilibhit | Bisalpur | Manpur Marori | 405273 | Vedkhera | 137 | 136 | 99% | Work In Progress | Not Certified |