Scheme Details
DISTRICT
Etah
AGENCY
Power Mech Projects Ltd
SCHEME ID
20060951
SCHEME NAME
BARAULI
ESTIMATED COST
176.64
EXPENDITURE
132.31
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6634.00
Meter
Length Laid
7431.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etah | Shitalpur | Barauli | 399558 | Barauli | 99 | 99 | 100% | Har Ghar Jal | Certified |
| 2 | Etah | Shitalpur | Barauli | 399559 | Kunetha Ta Barauli | 61 | 61 | 100% | Har Ghar Jal | Not Certified |
| 3 | Etah | Shitalpur | Barauli | 399560 | Sahaspur Barauli | 135 | 134 | 99% | Work In Progress | Not Certified |