Scheme Details
DISTRICT
Bulandshahr
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20061124
SCHEME NAME
Jalalpur Jah & Asadpur Gher & Burhanpur Khurd WSS
ESTIMATED COST
459.59
EXPENDITURE
148.98
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21501.00
Meter
Length Laid
20500.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Danpur | Asadpur Gher | 393781 | Asadpur Gher | 432 | 425 | 98% | Work In Progress | Not Certified |
| 2 | Bulandshahr | Danpur | Jalalpur Jatt | 393783 | Jalalpur Jatt | 366 | 366 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bulandshahr | Danpur | Jalalpur Jatt | 393784 | Burhanpur Khurd | 186 | 178 | 96% | Work In Progress | Not Certified |