Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Hardoi
AGENCY NCC Ltd.
SCHEME ID 20061194
SCHEME NAME NEER JJJM
ESTIMATED COST 560.01
EXPENDITURE 416.57
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 44
Procured 44 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 28710.00 Meter
Length Laid 28710.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Hardoi Ahirohi Neer 413070 Neer 1479 1450 98% Work In Progress Not Certified