Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20061217 | NAIKPUR HATIMPUR (GOGP) | 384.78 | 253.29 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 13482.00 | 14042.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Bilagram | MITMITPUR | 412675 | KUBERPUR | 84 | 83 | 99 | Work In Progress | Not Certified |
| 2 | Hardoi | Bilagram | Nekpur Hatimpur | 412704 | Nekpur Hatimpur | 400 | 395 | 99 | Work In Progress | Not Certified |
| 3 | Hardoi | Bilagram | Nekpur Hatimpur | 412705 | Masoodpur | 137 | 137 | 100 | Har Gar Jal | Not Certified |
| 4 | Hardoi | Bilagram | MITMITPUR | 412762 | Mitmitpur | 104 | 103 | 99 | Work In Progress | Not Certified |