Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Rithwik-Koya (JV) | 20061240 | Bhuvani water supply scheme | 353.63 | 185.58 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | Yes | 0 | NA | No | 10318.00 | 10318.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Ghughuli | Bhuwani | 454339 | Bhuwani | 563 | 511 | 91 | Work In Progress | Not Certified |
| 2 | Maharajganj | Ghughuli | Bhuwani | 454340 | Chuwani | 164 | 130 | 79 | Work In Progress | Not Certified |