Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Fatehpur Power Mech Projects Ltd 20061322 SAIBSI & UMARPUR 335.23 92.56 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 1 0 25 25 Yes 0 NA No 16169.00 16002.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Fatehpur Asother Saibsi 428182 Saibsi 195 188 96 Work In Progress Not Certified
2 Fatehpur Asother Saibsi 428183 Jamaini 133 133 100 Har Gar Jal Not Certified
3 Fatehpur Asother Umarpur 428184 Umarpur 236 167 71 Work In Progress Not Certified