Scheme Details
DISTRICT
Ayodhya
AGENCY
VSA
SCHEME ID
20061365
SCHEME NAME
PACHHIYANA WSS
ESTIMATED COST
518.90
EXPENDITURE
312.81
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
31552.00
Meter
Length Laid
29254.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Tarun | Pachhiyana | 437404 | Pachhiyana | 881 | 870 | 99% | Work In Progress | Not Certified |