Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | VSA | 20061607 | KAKRAHI & BARA & KEWALAPUR W/S | 559.73 | 341.95 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 35266.00 | 28014.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Tarun | BARA | 437377 | MAHOLIYA | 53 | 53 | 100 | Har Gar Jal | Not Certified |
| 2 | Ayodhya | Tarun | Kakrahi | 437378 | Kakrahi | 193 | 193 | 100 | Har Gar Jal | Not Certified |
| 3 | Ayodhya | Tarun | BARA | 437379 | BHAGWANPUR | 30 | 30 | 100 | Har Gar Jal | Not Certified |
| 4 | Ayodhya | Tarun | BARA | 437380 | Bara | 145 | 145 | 100 | Har Gar Jal | Not Certified |
| 5 | Ayodhya | Tarun | Kevlaapur / Takmeenganj | 437381 | Dharm Pur | 94 | 94 | 100 | Har Gar Jal | Not Certified |
| 6 | Ayodhya | Tarun | Kevlaapur / Takmeenganj | 437382 | Kevlaapur / Takmeenganj | 419 | 419 | 100 | Har Gar Jal | Not Certified |